House Project Pages
November 18th, gluelam beams in place and floor joists installation started. Jeremy and Sterling have taken to wearing long pants, summer is now over.
Jeremy must have prayed to the wood gods he keeps mumbling "no more concrete, no more concrete".
15 pieces of steel and every screw and weld in the correct spot. Jeremy and Sterling put some wood up b/4 the rains came.
November 16th Steel and Wood, King Crane set in place our steel and wood beams. Thursday the floors start going in. This will make JILL very happy.
11/11/99 Garage door framing and my Katie. YESSS a Garage with a bathroom.
Pony wall for upstairs bedroom.
Upper foundation is cut and pier holes (16" round and up to 15" feet deep) are being drilled.
Done Digging August 9th
In goes the steel, 20 feet